Skip To Content

Pavement Management 2025 Project

Posted on: 2025/04/02

The City of San Ramon (“City”) will accept sealed bids for its (“Project”) Pavement Management 2025 Project (CIP No. 000015).

Bid Documents
Plans
Notice Inviting Bids
Bid Opening Form - dated April 30, 2025

The following Bid Results reflect the results as read at the time of Bid Opening Results may change once bid analysis is completed.

Project Name: Pavement Management 2025 Project
Project No: CIP 000015
Date: April 30, 2025
Project Manager: Suzy, Edwards  (925) 973-2667
Engineer's Estimate $2,910,037.16

 No.   CONTRACTORS  BASE BID
 1 Pavement Coatings Co.  $2,266,831.55
 2 Doolittle  Construction, LLC DBA Doolittle Road Construction  $2,119,000.00
 3  American Pavement Systems, Inc. $1,874,569.07
 4  VSS International, Inc.  $1,794,120.00

Planned Bid Schedule - The following schedule is provided for planning purposes based on current information. However, all dates are subject to revision, including the SOI Deadline, and may be amended by addenda to this Bid package:

Bid Posting: Wednesday, April 2, 2025
Request for Information: Wednesday, April 23, 2025 by 5:00 PM
Bid Opening: Wednesday, April 30, 2025 at 2:00 PM
Bid Protest Date: Friday, May 2, 2025 by 5:00 PM
Bid Award Date: Tuesday, May 27, 2025
Estimated Construction Start: Monday, June 23, 2025
Estimated Construction Completion: Tuesday, September 16, 2025

Questions? Please contact Suzy Edwards


Status

Closed on 04/30/2025